Idlewood Roundabout – Schedule / Status Update

From City Transportation Engineer Michael B. Sawyer:

Mr. Woodson / CM Agelasto: I trust all is well.

Per your request, please see the schedule below for the Idlewood Roundabout construction. We are currently in the process to acquire the necessary right-of-way (ROW).

Event Estimated Completion Date
Plan Complete Aug, 2015
Right of Way Aug./Sept., 2015
Bid Advertisement Sept., 2015
Award Contract if successful bid process Dec., 2015
Start Construction Jan., 2016
Complete construction April, 2016